Through Normal Mode. It usually takes 10-15 days after receipt of all the necessary Documents, The breakup of the Number of days is as follows:
| Activity |
Days |
| Taking Digital Signature of Directors |
1 Day |
| Taking Directors Identification Number (DIN) |
1 Day |
| Reservation of the name of the Company |
5 Days |
| Preparation of other Document such as MOA, AOA, Forms etc |
2 Days |
| Filling of Documents with Authorities |
1 Days |
| Getting Final Certificate of Incorporation |
5 Days |
| Total Number of Days |
15 Days |
Through Fast Approval- It Usually Takes 4-5 days after receipt of all the necessary Documents.
| Activity |
Days |
| Preparation of all Document such as MOA, AOA |
1 Day |
| Taking Digital Signature of Directors |
1 Day |
| Taking Directors Identification Number (DIN) |
1 Days |
| Filling of Documents with Authorities |
1 Days |
| Getting Final Certificate of Incorporation |
1 Days |
| Total Number of Days |
5 Days |